Plan review

Also called plans review, permit review

The stage where a building department's reviewers read your submitted plans against the adopted code and either approve them or issue comments you must resolve.

When it applies

In the permitting lifecycle, plan review applies during Plan review.

  1. Setup: does not usually apply
  2. Preparation: does not usually apply
  3. Submission: does not usually apply
  4. Plan review: applies at this phase
  5. Permit issued: does not usually apply
  6. Inspections: does not usually apply
  7. Closeout: does not usually apply

Plan review is the stage where the building department actually reads your submittal. Reviewers compare the drawings and calculations against the adopted building code, the local amendments to it, and the zoning rules that apply to the site.

A project is rarely reviewed by one person. Depending on scope, separate reviewers look at structural, electrical, plumbing, mechanical, energy, zoning, fire, and sometimes floodplain or environmental aspects. Each discipline can approve, or return comments, independently.

Cycles

Review is iterative. The first pass usually produces a set of comments. You resolve them, resubmit, and the reviewers check your responses. Each round trip is a review cycle. Two cycles is a good outcome on a nontrivial project; four or five is common when the first submittal was thin.

What reviewers are looking for

Reviewers are checking that the design is code compliant and that the drawings say so clearly enough to be verified. A design can be perfectly buildable and still draw comments because the drawings do not show the reviewer what they need to see. A large share of comments are about missing information rather than about bad design.

Where the time actually goes

Departments publish target review times, and those targets usually describe one cycle. A project quoted at 10 business days that goes through three cycles has taken six weeks of review, plus your own turnaround time on each set of comments.

Common questions

How long does plan review take?
It varies widely by jurisdiction, permit type, and workload. Simple residential permits are often reviewed in one to three weeks; complex or commercial projects can take a month or more per cycle. The bigger variable is usually the number of review cycles rather than the length of any single one, which is why a clean first submittal matters so much.

In the Permit Saige app

Help Center articles require a Permit Saige account.

Rules vary by jurisdiction

This definition is general. How plan review is handled in practice is set by the building department that permits your property. Find yours in our free directory.

Last reviewed September 4, 2026